Check the contract accounts
The current phase considers solar projects for commercial customers on tariffs 225 or 225A. Battery storage is required. Eligible customers may form a cooperative for a shared plant. Under the amendment dated 14 July 2026, the cooperative representing the participants supplies the percentage of production allocated to each eligible electricity account.
Interpret the 70 MW allocation
The pilot phase earmarks a total of 70 MW on the island of Mauritius. That figure gives no indication of capacity left at a specific connection point. The ceiling is 4 MW per site. Annual generation can be sized up to 150 per cent of eligible customers’ annual electricity requirements. Battery storage must at least cover their demand during peak hours.
Get a connection assessment
Gather monthly bills for each participating account and record the peak-period load. CEB determines the final allowable capacity through a network survey or network impact assessment. Download the current application and draft connection agreement and ask about capacity at your site before committing to equipment. The scheme provides a route for customer projects. Procurement of public works follows separate tender procedures.
Your next step
Ask the designer to size storage using the actual peak-period load profile as well as the annual energy requirement.